Kirk Project Works on Site Commenced 23rd January 2023

Kirk Project Works on Site at the end of the first week

This phase of the Kirk development has been possible due to grant aid from:

Scaffolding has been erected at the Kirk and the roof slates have been stripped with temporary roof protection in place. 16th March 2023

Roof repairs

Lime Harl in progress May 2023

Anchor stone

April 2024 and works continue

January 2025. Final Phase of the Papa Stour Kirk Development

The main contractor LTM group has been appointed and will be on site shortly

This final phase of the Kirk development has been possible due to grant aid from

March 2025
Joinery work including refixing the original timber ceiling, adding roof insulation and starting to refix the pulpit